目前,放射性“三废”设施治理工程部承担着“三废”设施治理专项工程的4个项目,分别是“放射性排风中心治理工程”、“163#放射性废液暂存库”、“中放废液输送系统建设工程”和“低放废液管网更新改造工程”。2010年,工程部按计划完成了各项目的节点目标,资金完成率均在90%以上。“放射性排风中心治理工程”完成四方交工验收和联合试运转,资金完成率为100%;“163#放射性废液暂存库”完成土建主体结构封顶、室内安装任务70%等,资金完成率为94%;“中放废液输送系统建设工程”完成计量间土建结构封顶、300米中放管网施工等,投资完成率为100%;“低放废液管网系统更新
Currently, the Radioactive Waste Management Facilities Engineering Department undertakes four projects of special facilities for the treatment of ”three wastes“, namely radioactive waste temporary storage for Radioactive Drainage Center Control Project, Library ”, “ in the release of waste water delivery system construction project ”and “ low-emission liquid pipe network renovation project ”. In 2010, the Ministry of Construction completed the goal of each project according to the plan and the capital completion rate was over 90%. “Radioactive exhaust center management project ” to complete the Quartet inspection and acceptance of joint commissioning and commissioning, the capital completion rate was 100%; “163 # radioactive waste temporary storage ” to complete the main structure of civil engineering cap, 70% of indoor installation tasks , The completion rate of 94% of the funds; “in the release of waste water delivery system construction project ” to complete the measurement of civil engineering structures capping, 300 meters in the pipe network construction, investment completion rate was 100%; "low-level waste pipe Network system update