一、概述汉江丹江口水利枢纽,根据坝址处水(?)、地质、地形条件结合水工布置,经过详细的施工导流规划的论证,采用分两期导流,第一期先围右岸的方案。由于坝址处20年一遇洪峯流量达34,500秒公方,纵向围堰段平均流速达10秒公尺左右,在深达20余公尺河床复盖层上建造抵挡如此巨大流速的纵向围堰是十分困难。根据进度安排,导流规划提出先作一道低水围堰防御11月至5月份20年一遇的7,830秒公方流量,在低水围堰的保护下再修建抵御汛期洪水的高水围堰。本文仅就低水围堰修筑中的几点体会提出讨论。由于施工期间收集资料不够,水平也很有限,不当之处希予指正。
First, an overview of Hanjiang Danjiangkou Water Control Project, according to dam site at the water (?), Geological and topographic conditions combined with hydraulic layout, after detailed construction diversion planning demonstration, the use of two phases diversion, the first phase of the first right bank Program. Due to the flood peak flow of 34,500 seconds at the dam site in 20 years and the average flow velocity in the longitudinal cofferdam section of about 10 seconds, a longitudinal wall to resist such a huge flow rate is built on a depth of 20 meters of bed cover Weir is very difficult. According to the schedule, the diversion plan proposed to first make a low-water cofferdam to prevent the public flow of 7,830 seconds from November to May in 20 years, to build a high-water cofferdam under the protection of low-water cofferdam to resist the flood in flood season . This article only on the low water cofferdam construction experience in a few discussions. Due to insufficient information collected during the construction period, the level is also very limited, and any improper measures should be corrected.