6月16日,中冶赛迪承担的阿塞洛-米塔尔集团德国不来梅钢厂3号高炉大修供货项目全部货物在上海港罗泾码头顺利发船。这标志着中冶赛迪与世界最大钢铁集团的首次正式合作获得成功,为中冶赛迪与阿塞洛-米塔尔集团的进一步合作奠定了良好的基础。中冶赛迪于2008年2月24日签订该供货合同,5月8日完成所有详图设计,4月26日开始加工制造。由于
June 16, MCC Sedi assumed the ArcelorMittal Group, Bremen, Germany, No. 3 blast furnace overhaul supply of all goods shipped in Shanghai Port Luojing Ferry smoothly. This marked the first successful cooperation between CCID and the largest steel group in the world, laying a good foundation for the further cooperation between CCID and ArcelorMittal Group. MCC CCID signed the supply contract on February 24, 2008, completed all detailed design plans on May 8, and started manufacturing and processing on April 26. due to