论文部分内容阅读
桥电二厂 2台 1 2 5MW机组自 1 995年、1 996年相继投运以来 ,其凝结水含氧量一直处于超标范围之内 ,严重影响了桥电二厂热力设备的运行健康水平和汽、水品质总合格率 ,经过反复试验与检查 ,从凝结器负压系统、疏水系统以及真空除氧装置等方面找到了凝结水含氧量长期超标的真正原因 ,经改进设备后 ,消除了隐患 ,凝结水含氧量达到部颁标准
Since the first 125MW units of Qiaodi Power Plant were put into operation one after another from 1995 and 1996, the oxygen content of the condensate water has been kept within the scope of the standard, seriously affecting the operation and health of the thermal power plant of Qiaodi Power Plant and Steam, water, the total qualified rate of qualified, after repeated testing and inspection, from the condenser negative pressure system, the hydrophobic system and vacuum oxygen scrubbing device to find a real long-term excessive oxygen content of the condensate water, after the improvement of equipment, eliminate Hidden trouble, the oxygen content of condensed water to meet ministerial standards