海南省海口市长城堵海防潮堤加固工程中的防潮排洪闸为松软粗砂及粘土地基,承载力达不到设计要求,采用了深层搅拌粉喷桩加固新技术。加固工程在编制概算时因缺乏粉喷桩定额,设计单位收集了有关资料,在研究和分析的基础上估列了单价。一年后海南省水利局颁发的定额中就有此定额。按此定额编制的单价与原估列的单价相差甚微。这说明采用此定额是较为合理、正确的。
Haikou City, Hainan Province, the Great Wall of the sea wall to prevent moisture in the flood control flood gates for the loose grit and clay foundation, the bearing capacity of less than the design requirements, the use of deep mixing powder spray pile reinforcement technology. Reinforcement project in the preparation of budget estimates due to the lack of fixed quota, design units to collect the relevant information, based on research and analysis of the unit price is estimated. One year later, Hainan Provincial Water Conservancy Bureau issued a quota for this quota. Click here to set the unit price and the original estimate of the price difference is very small. This shows that the use of this quota is more reasonable and correct.