论文部分内容阅读
这种水池是将池壁预制成L型板块,施工时靠自身直立,壁板底座伸出钢筋与水池底板伸出钢筋焊接在一起,再在接缝处浇混凝土。L型壁板装配水池实质上是将以往现浇水池在池壁根部的施工缝移到底板边缘处。这种结构型式,施工简单,整配化程度高,整体性好。容易上马,便于推广。在常州市九里巷增压泵站首次建造了两座容量为5000米~3的L型水池。其剖面见下图。尺寸:水池平面呈矩形,长39.9米、宽36.1米,有效水深为3.5米,容量为5000米~3,埋深为1.15米,
The pool is pre-formed into the L-shaped plate wall, erected on their own by the time, the base plate protruding out of the steel and the pool floor extended rebar welded together, and then poured concrete in the joints. The L-shaped wall assembly pool essentially moves the construction joints of the past cast-in-place basins at the root of the pool walls to the edge of the floor. This type of construction has a simple construction, a high level of integration, and a good overall quality. Easy to launch, easy to promote. Two L-shaped tanks with a capacity of 5,000 meters to 3 were built for the first time at the Jiuli Lane booster pumping station in Changzhou. The profile is shown in the figure below. Size: The pool surface is rectangular, 39.9 meters long and 36.1 meters wide, with an effective depth of 3.5 meters, a capacity of 5,000 meters to 3, and a depth of 1.15 meters.