在主排水系统设计矿井水泵房,多级离心泵一般为一组工作,一套备用。系统一般采用手动操作,操作过程中,人的劳动强度的因素,启泵时间越长,自动化程度低,实现峰谷的控制方式,它是不容易的,不能满足现代化煤矿管理的要求。因此,主排水系统的自动化控制是非常重要的。国家安全生产监督管理在2009年12月1日实施的《预防和煤矿水调节》第一百一十八调控管理:严重威胁矿井水,要实现井下泵房无人值守和地面远程监控。
In the main drainage system design mine pump room, multi-stage centrifugal pump is generally a set of work, a set of spare. The system generally adopts manual operation. During operation, the factors of labor intensity, the longer pump-start time, the lower degree of automation and the control of peak and valley are not easy and can not meet the requirements of modern coal mine management. Therefore, the automatic control of the main drainage system is very important. State Administration of Production Safety Supervision and Control on December 1, 2009, “Prevention and Control of Coal Mine Water” The 118th Regulatory Management: A serious threat to mine water, unmanned downhole pump room and ground remote monitoring.