在川气东送管道一期投产过程中,为了确保新清溪1井正常生产,应急投产川维支线。在燕子窝-天生段和天生-金山段封存氮气隔离段,采用“气推气”置换工艺,对站场工艺管道与长输管道进行同步置换。利用阀室内的调流阀进行流量调节,控制置换速度,缓解气井油层的套管压力。采取干支线联通反输工艺流程,利用管存气确保普光净化厂的顺利投产。通过对注氮、置换、升压、流速控制等作业参数的具体分析,阐述了管道投产置换中的关键控制点及技术措施。(表2,图2,参10)
During the first phase of production of the Sichuan-East Gas Pipeline, Chuanwei Extension was put into operation in an emergency to ensure the normal production of Xinqingxi 1 well. In Swallow Nest - natural and natural - Jinshan Segment of nitrogen isolation segment, the use of “gas push gas ” replacement process, the site of the process pipeline and long-distance pipeline replacement simultaneously. The use of the valve chamber flow control valve to regulate and control the replacement rate to ease the gas well casing pressure. Adopt dry branch line Unicom reverse transport process, the use of tube storage gas to ensure the smooth operation of Puguang Purification Plant. Based on the concrete analysis of operation parameters such as nitrogen injection, displacement, pressure rise and flow rate control, the key control points and technical measures in pipeline replacement are expounded. (Table 2, Figure 2, reference 10)