克里沃罗格中部采选公司露天矿开采两层平均厚度为95米和127米的急倾斜矿层。该露天矿下部水平和端帮采用汽车运输矿岩,矿石运至转运站,从而保证了旷山工程具有较高的延深速度。在转运站内,主要是利用ЭКГ-8型电鏟向铁路运输(载重80和100吨的自翻矿车)转运矿石和部分岩石。由于露天矿到选矿厂的运距大(约12公里),而且为了提高汽车运输岩石的效率,故在露天采矿场内设
In the Kliwolfo grid mining company, the open pit mines two steep grade coal mines with an average thickness of 95 and 127 meters. The lower part of the open pit mine and the end of the use of motor transport of ore, ore transported to the transfer station, thus ensuring the Kuang Shan project has a higher depth of extension. In the transfer station, the ore and some rocks are mainly transported to the railroad (self-turning trucks carrying 80 and 100 tons) using the ЭКГ-8 electric shovel. Due to the large distance (about 12 km) between the open-pit and the concentrator and in order to increase the efficiency of rock transportation by car,