建于50年代的很多沿海老闸急需加固维修。但因原工程设计先天不足,常常在施工中为拆除老闸门等大件而费时费力。最近淮阴水利建设集团有限公司在承建烧香河闸加固工程中,采用钢管搭设操作平台方案拆除旧闸,成功地解决了上述问题,取得了缩短工期、节省费用的很好效益。 1957年建于连云港市的烧香河闸,为带胸墙的开敞式挡潮节制闸,共6孔,每孔净宽8m,经过40多年运行,老化现象非常严重,淮阴市水利建设集团有跟公司于去年2月中标该闸加固工程。因加固工程的子项目都为水上部分,故淮阴市水建从节省经费出发,决定不用打围堰干地施工,选择在水中搭设平台施工。在施工中遇到的最大难题就是
Many coastal sewers built in the 1950s are in urgent need of reinforcement and repair. However, due to inherent deficiencies in the original engineering design, it is often time-consuming and labor-intensive to demolish large sluices such as old sluices during construction. Recently, Huaiyin Water Conservancy Construction Group Co., Ltd. in the construction of burning Xiang River sluice reinforcement project, the use of steel pipe erection of operating platform program to remove the old gate, successfully solve the above problems, and achieved shortened duration and cost savings of good benefits. Built in 1957 in Lianyungang City, burning incense River Gate, with a chest wall of the open tidal control gate, a total of 6 holes, each hole net width of 8m, after 40 years of operation, the aging phenomenon is very serious, Huaiyin City Water Construction Group with the company in Last February won the gate reinforcement project. As the subprojects of the reinforcement project are all waterborne parts, the water construction in Huaiyin City starts from saving funds and decides not to construct the cofferdam dry-land and chooses to build a platform in the water. In construction encountered the biggest problem is