一、概况紫荆关三级水电站位于河北省易县五一渠渠道上,是建设易县农村电气化电源的骨干工程。电站设计水头为80.0m,总装机容量为3,750kW。工程始建于1984年6月,竣工并正式运行于1986年10月,整个电站工程造价为357万元(含输电线路12万元),是目前河北省单位千瓦投资最低,且工期较短的一座水电站。其主要技术经济指标如表1所列。
First, the overview Bauhinia level three hydropower station is located in Yi County, Hebei Yi Wu canal channels, is the construction of rural electrification of Yixian backbone of the project. The design head of the power plant is 80.0m, with a total installed capacity of 3,750kW. The project was established in June 1984 and was completed and formally operated in October 1986. The entire project cost 3.57 million yuan (including 120,000 yuan of transmission lines), which is the lowest investment in kilowatts of units in Hebei Province with a short construction period A hydropower station Its main technical and economic indicators are listed in Table 1.